Estimated schedule provided by JMR which is subject to change due to DOT permitting. JMR may have to return in the spring to complete if needed.
The proposed schedule is as follows below:
Week of 9/21-9/25/2026
Mobilization
Clearing trees
Remove Existing Lampposts
Week of 9/28-10/2/2026 (East Side of Main Street Only)
Sidewalk/Paver Demo
Place Subbase
Week of 10/5-10/9/2026 (East Side of Main Street Only)
Sidewalk/Paver Demo
Place Subbase
Prep and place concrete curb
Form and pour 4inch and 6inch walk
Week of 10/12-10/16/2026 (East Side of Main Street Only)
Form and pour 4inch and 6inch walk
Form and place decorative walk
Week of 10/19-10/23/2026 (East Side of Main Street Only)
Form and place decorative walk
Full depth asphalt placement
Week of 10/19-10/23/2026 (West Side of Main Street Only)
Sidewalk/Paver Demo
Place Subbase
Week of 10/26-10/30/2026 (West Side of Main Street Only)
Sidewalk/Paver Demo
Place Subbase
Prep and place concrete curb
Week of 11/2-11/6/2026 (West Side of Main Street Only)
Sidewalk/Paver Demo
Place Subbase
Prep and place concrete curb
Form and pour 4inch and 6inch walk
Form and place decorative walk
Week of 11/9-11/13/2026 (West Side of Main Street Only)
Form and place decorative walk
Full depth asphalt placement
Week of 11/9-11/13/2026 (Both Sides of Main Street)
Place planting mix/trees/subbase
Install porous pavement
Week of 11/16-11/20/2026 (Both Sides of Main Street)
Place planting mix/trees/subbase
Install porous pavement
Install acrylic pavement markings
Install lighting (Tentative based on delivery 10-12 week lead time)
Punchlist/cleanup